SMRL Home Stanford Magnetic Resonance Laboratory
HOME USERS and RESEARCH INSTRUMENTATION NMR TIME REQUEST
800 600 500

600 MHz Varian UNITYINOVA
System Update

Console Installation Schedule and Progress (Varian, Inc.):

  • Tuesday, May 14 [Arthur]
    • Bad component traced to receiver board. Replaced.
    • Re-map.
  • Monday, May 13 [Arthur]
    • Troubleshooting.
  • Saturday, May 11 [Arthur]
    • Could not converge shims. System is noisy. Suspect a bad component.
  • Friday, May 10 [Arthur and co.]
    • Mapping aborted overnight. Overheating problems. Setup again with fan blowing on laptop and controller box.
  • Thursday, May 9 [Arthur and co.]
    • Map and shim cryoshims.
    • Setup room T shim mapping overnight.
  • Wednesday, May 8 [Arthur and co.]
    • Continue console wiring.
    • Clean-up TMC leg tubing.
    • Unpack and setup manostat.
    • Relocate helium and nitrogen level meter and clean-up wiring.
    • Loosely insert upper stack.
    • Setup field mapping equipment.
  • Tuesday, May 7 [Arthur and co.]
    • Unpack and roughly position the console, console interface box, and preamplifiers.
    • Rough lay of console wiring.
  • Wednesday, May 1 [Robert Short]
    • Conclude site evaluation.
  • Tuesday, April 30 [Robert Short]
    • Setup site evaluation equipment (vibrations, electrical, RF, etc.)


Magnet Installation Schedule and Progress (Oxford):
  • Thursday, May 2 [Ian Davies]
    • Cryoshims.
  • Wednesday, May 1 [Ian Davies]
    • Energizing magnet to 120 amps.
    • Magnet made it to field!
    • Top-up helium and let magnet sit persistent overnight.
  • Tuesday, April 30 [Ian Davies]
    • While energizing magnet to 120 amps, quenched at 110 amps.
    • Helium level was around 50% at quench point. Almost all helium boiled off. Top-up helium.
    • Re-energize to 75 amps and sit persistent overnight.
  • Monday, April 29 [Ian Davies]
    • Energize magnet to 75 amps. Sit persistent overnight.
  • Weekend of April 27/28 [Andy Shepheard]
    • Continue to pull vacuum on dewar.
    • Filled helium dewar.
  • Friday, April 26 [Andy Shepheard and Ian Davies]
    • Continue to pull vacuum on dewar.
    • Oxford leak detector and "pump and purge kit" arrived.
    • Assemble and mount helium manifold.
    • Check for vacuum dewar leaks.
    • Cooled and filled nitrogen dewar.
    • Cooling helium dewar with nitrogen dewar boiloff.
  • Thursday, April 25 [Andy Shepheard]
    • Continue to pull vacuum on dewar.
  • Wednesday, April 24 [Andy Shepheard]
    • Picked up 3-ton chain hoist from Hertz Equipment Rental.
    • Raised tripod another notch and replaced the hoist.
    • Raised the magnet up, rotated to orient helium fill port towards front of magnet pad and vacuum port to rear of magnet pad.
    • Roughly positioned the TMC leg bases, loosely bolted on the leg braces and upper sections.
    • Centered the legs as much as possible, and lowered and centered the magnet onto the legs.
    • Tightened the bolts.
    • Removed the magnet shipping restraints.
    • Cleaned and installed the plates and O-rings to cover the shipping restaint holes.
    • Cleaned the quench drop-out plate and O-ring.
    • Start pulling vacuum on the dewar (holding drop-out plate in place until vacuum is enough to hold into place [Drop-plate actually supposed to come attached to a spring and restraining rod on the magnet, but the screw holding the spring to the plate worked itself off during transit. Darn near impossible to put the spring and screw back on so abandoned the restraining rod, spring and retaining screw.]).
    • Assembled the TMC leg bladder control lines and tested with the compressed air line plumbed to the magnet.
  • Tuesday, April 23 [Andy Shepheard]
    • Liquid and gaseous nitrogen and helium delivered to site.
    • Oxford tripod and pump delivered to site.
    • Unpacked magnet.
    • Magnet and pallet pallet-jacked to concrete magnet pad.
    • Tediously lifted and slid partially onto magnet pad.
    • Tripod and hoist erected around magnet.
    • Aid of hoist, pallet jack, broom handles, 2x4 lever, muscle power, magnet was positioned in the center of the pad.
    • Leg brackets bolted to the magnet.
    • Magnet released from pallet.
    • Attempted to hoist magnet onto its legs, but a quirk in the chain hoist brought over by Oxford did not allow magnet to be jacked up high enough. Abort and locate a different chain-hoist.
    • Possible source is Hertz Equipment Rental in San Jose.


Renovation Project Schedule:
Schedule as of 3/20/02 - 600projsched-020320.pdf
Anticipated completion of renovation project: Week of April 1

600 system installation start: Week of April 22
Renovation Project Progress:
  • Wednesday, May 8
    • Replace chilled water flow meter (0-1 L) by 600 with new one of appropriate size (0-5 L).
  • Friday, April 26
    • Pre-punch list walk through.
  • Wednesday, April 24
    • Santa Clara county final inspection. A few minor details need to be addressed, but otherwise project is signed off.
  • Tuesday, April 16
    • Remove panel above front door header to investigate wiring.
  • Monday, April 15
    • Found that the chiller pump was wired with the wrong rotation (phases). Correcting it solved the tripping problem.
  • Thursday, April 11
    • Paint second layer of 5 gauss circle.
    • Fire Marshall inspection. Approved.
    • Insulating chiller lines.
    • Label plumbing.
    • Continue external plumbing for chiller.
  • Wednesday, April 10
    • Paint first layer of 5 gauss circle on floor and magnet pad.
    • Continue external plumbing for chiller.
    • Insulating chiller lines.
    • Troubleshooting chiller pump (trips off after a couple of minutes).
  • Tuesday, April 9
    • Layout, clean, and etch area for 5 gauss circle.
    • Continue external plumbing for chiller.
    • Insulating chiller lines.
  • Monday, April 8
    • Closed cycle chiller test.
  • Friday, April 5
    • Continue external plumbing for chiller.
  • Thursday, April 4
    • Continue external plumbing for chiller.
    • Painting (internal conduit and touch-up [white]; external conduit, pipes, touchup [beige], chiller [black].
    • Minor electrical work.
    • Complete installation of Store-Wall peg board.
    • Patch work.
    • Continue general cleanup.
    • Inspection.
  • Wednesday, April 3
    • Continue external plumbing for chiller.
    • Mount chiller to pad.
    • Continue electrical. Cap 3 phase lines for helium compressors. Extend existing 800 UPS tie-ins.
    • Complete installation of base board strips around magnet pad.
    • Start installation of Store-Wall peg board panels.
    • Patch work.
    • Continue general cleanup.
  • Tuesday, April 2
    • Continue plumbing for internal chilled water locations.
    • Complete plumbing for internal compressed air locations.
    • Start plumbing at chiller.
    • Continue electrical. Complete wiring of external power cutoff box for chiller.
    • Install door-drops to seal cracks at bottom of doors.
    • Install stub wall cable pass through conduit.
    • Start installation of base board strips around magnet pad.
    • Start general cleanup.
  • Monday, April 1
    • Compressor capacity upgrade (new pulleys, reassemble).
    • Air-dryer capacity upgrade (complete plumbing).
    • Cover HVAC register above magnet location.
    • HVAC rebalancing.
    • Continue plumbing for internal chilled water locations. Scheduled fire alarm shutdown for internal soldering.
    • Continue electrical. Complete load center and plug strip. Hang track lighting in place of old light fixture. Start wiring of external power cutoff box for chiller.
    • Complete weather proofing of east facing windows.
  • Friday, March 29
    • Complete window tinting.
    • Compressor capacity upgrade (disassemble pulley/flywheel guards, remove pulleys).
    • Air-dryer capacity upgrade (remove old desiccant dryer, mount new dessicant dryer, initial plumbing).
    • Continue plumbing.
    • Initial mounting of chiller to pad by attaching brackets to the wheel axle bolt and bolting bracket to the pad.
    • Continue electrical. Wire pulls. Wiring of load center.
  • Thursday, March 28
    • Electrical conduit runs almost complete.
    • Mounted oxygen sensor and ran conduit to control box.
    • Started mounting and wiring the load center and plug molding that will distribute power to spectrometer.
    • Hung brackets to hold external power cutoff box for chiller.
    • Continue window tinting.
  • Wednesday, March 27
    • Continue plumbing. Scheduled fire alarm shutdown to complete tie-in to domestic water line.
    • Start window tinting of east facing windows.
    • Start weather stripping of east facing windows.
    • Moved chiller to outside pad (pallet jack and fork lift).
    • Continue electrical conduit runs: extended the three runs out from panel room, through bathroom/work bench false ceiling into main lab area, extended chiller supply conduit up from the east facing window termination accross the ceiling, added a second run for the 800 helium compressor line
  • Tuesday, March 26
    • Continue electrical conduit runs: start three runs from panel and one run along existing conduit runs by east facing windows (for chiller power).
    • Removed light fixture above magnet location.
    • Walk through by HVAC specialist for air-load re-balancing.
  • Monday, March 25
    • Continue pipe run for chiller water. Run line above SMRL work bench false ceiling, over the bathroom, into the electrical closet, and tie into existing valved branch from main domestic cold water source. (Smoke from soldering triggered smoke detector in electrical closet. PAFD responded to shut off alarm. Need to schedule alarm shutdown to complete the work.)
    • Started electrical conduit from panel.
  • Friday, March 22
    • Adjusted rebar for magnet pad.
    • Inspected by special inspector (due to 3000 psi specification for pad concrete).
    • Poured concrete for the pads.
    • Walk through by window tinting contractor.
  • Thursday, March 21
    • Remove floor tiles at magnet concrete pad location.
    • Rebar and forms for magnet and chiller concrete pads.
    • Initial inspection for pad rebar and forms.
    • Compressor shutdown to T into compressed air lines to supply 600. (Branch from compressed air line has a leak at the valve joint...)
    • Continue piping runs through adjacent classroom and Anderson lab computer room ceilings; penetrates into false ceiling space above SMRL work bench area.
  • Wednesday, March 20
    • Core through exterior walls for piping and electrical conduit pass-throughs.
    • Mount some pipe runs from bored holes to rough source location (clean dry air line, 600 chilled water lines).
    • Chiller supply water will come from domestic cold water line located in SMRL bathroom area. Started this pipe run from rough chiller location, extended around building, and through adjacent classroom ceiling. Need to pass through dead space between classroom and SMRL bathroom (Update 3/21: turned out to be Anderson computer room) to tie into SMRL domestic cold water line.
  • Tuesday, March 19
    • Mount uni-struts to exterior walls for source water, chilled water, and compressed air piping.
    • Rough mounting of some piping to uni-struts.
  • Monday, March 18
    • Walk through by electrical contractor.
  • Thursday, March 14
    • Hang plastic sheeting for dust control in project area.
    • Prune foilage behind equipment shed where chiller is to be located.
    • Reverse swing of fence gate.

Bio-X Structural Biology School of Medicine Stanford University
© Stanford University, All Rights Reserved.
Feedback: Corey Liu (liuc@stanford.edu)